Stormwater drainage requirements are delaying plans for the Weigh Station, a proposed supermarket and restaurant development at 7723 S Main St. in Pine Plains, as engineers work to address high groundwater levels on the property.
Engineer George Schmidt told the Planning Board on Wednesday, Nov. 18, that the site’s high groundwater table requires an alternative drainage plan under New York state regulations. One option would be to reduce the project’s footprint, potentially eliminating the need for a zoning variance.
The current proposal exceeds the allowable building size and would require a variance, in addition to modifications to the stormwater management plan.
No representatives of the Weigh Station project attended Wednesday’s meeting because the plans must be revised before they can return to the board.
Board members expressed hope that the development would move forward.
The Planning Board also declared itself the lead agency for the project. A written resolution formalizing the designation is expected to be presented for a vote at the board’s next meeting, on Dec. 9.
Hudson Company revises site plan
Due to rising construction costs, the Hudson Company submitted an amended site plan that reduces the project’s size. Jamie Hamill, who owns the property at 2436 Route 83 presented the new plan to the board remotely, while LaBella engineer Kyle Bardwell attended the meeting in person.
The revised plan eliminates a corner building that was to house a showroom and apartment. Instead, the showroom will be incorporated into the main building.
“It’s still going to be beautiful,” Hamill assured the board.
Hamill is expected to present a visual rendering of the revised site at the Dec. 9 meeting. A public hearing on the amended site plan is scheduled for 7:35 p.m.
Affordable Mini Homes proposes new location
Dale Mitchell, owner of Affordable Mini Homes, proposed relocating the business from the north side of Stewart’s to 4 acres he owns on the south side. The proposed entrance would be through Pilch Drive.
The property would accommodate model homes as well as those that have been sold but are awaiting relocation.
Board members said Mitchell must submit a complete site plan, including surveys and drawings, before they can fully evaluate the proposal or consider approval.
“It seems like a reasonable thing for that location,” Planning Board Chair Michael Stabile said, closing the discussion.